Segment | Steel

VILLARES METALS S/A – Sumaré / SP – Brazil



VILLARES METALS S/A – Sumaré / SP – Brazil




  • Emphasis Factor: Effective of 50 employees => 49 months with ‘zero accidents’.

  • Technical management of the design, manufacture and assembly of the Dust Removal System of the Steelworks Furnace, with a total weight of 300 tons.
  • Technical management of the relocation, transfer and installation of the F-302 Furnace of the Rapid Steel Cell for Heat Treatment II, including: mechanics, boiler and utilities.
  • Technical management of the foundation of TOS 1 and 2 Machining Machines, Behringer and Thermal Treatment Area Quenching Furnaces.
  • Structural reinforcement of the Machining and Steelworks Building.
  • Management of general stop for maintenance of Cell 2 – Steelworks.
  • General stop management for maintenance and upgrades of the Lamination Blooming and Multiline Laminators.
  • Management of the modification of Layout of machines of the Finishing of Bars, aiming to guarantee continuous flow in the productive process.
  • Management of the adequacy of utilities near the Entrance Control II – CSTT building.
  • Corrosion Laboratory Construction Management – R & D; TOTO 2 generator room and CSTT generator room.
  • Management of the general stop for maintenance and design improvements in the VOD-1 System of Cell 1 – Steelworks.
  • Work management for the civil foundation of the press capacity 600 tons, of Forging Area.
  • Technical and commercial management of equipment dismantling contract in São Caetano do Sul and transport to Sumaré / SP, including: 01 Atlas press (capacity 2.000 tons), 01 Demag ingot manipulator (weight 120 tons) and 04 Laminating kilns .
  • Technical and commercial management of contract for dismantling of equipment in São Caetano do Sul, transportation to Sumaré / SP, refurbishment and electromechanical, civil and refractory installation of 07 furnaces of Forging Area.
  • Technical and commercial management of contract for the general reform of the chemical stripping of the wire drawing, including: civil, mechanical, electrical and utilities – Sorocaba Plant / SP.
  • Technical and commercial management of contract for general reform, adjustments and transfer of 03 cranes for Pindamonhangaba / SP Plant, with: BB-1 crane cap. 20/5 tons, Overhead crane – Forging Sector capacity 55/15 tons and bridge crane VIM – Steel Sector capacity 50/10 tons.
  • Contract management for São Caetano do Sul transfer to Sumaré / SP, refurbishment and electromechanical installation of equipment (furnaces, machining equipment and production machines), production areas
  • Cylinder Machining, Raw Finishing, Laminating Oven, Chemical Stripping, Machining & Fast Steel, Bar Finishing, Heat Treatment, Forging, Wire Drawing and Tract Station of Chemical Effluents.
  • Management of expansion of the Steelworks Area, installation of VOD System and Degassing for steel refining, including: project planning, contracting, civil & electromechanical works, commissioning and start-up, at Sorocaba Plant / SP.
  • Coordination of the Parade for General Maintenance of Laminated Train No. 5, including: planning, contracting, civil and electromechanical works – Sorocaba / SP.
  • Management of the Special Wires Drawing Unit, including: project planning, dismantling of the Wire Factory, in Santo André / SP (purchased by the company), transfer of equipment to the Sorocaba Mill, renovation and expansion of existing Building for installation of equipment, civil works, general equipment reform, electromechanical assembly, commissioning and operational start-up.
  • Coordination of the Rolling Mill Implementation – Rolling Mill Train No. 5, with a built area of ​​000 m², including: enterprise planning, basic and executive engineering, earthworks and infrastructure, civil, acquisition of national and imported equipment, electromechanical assembly, commissioning and operational startup.